| 1 |
Construction of (a) Drain from Siddik Payada road to Mamun house |
Galachipa Pourashava |
29800 |
180 Days |
| 2 |
Construction of (1) Culvert & earthen road west side of 130 barak and 130 barak south side Ghatla approach |
" |
12600 |
150 Days |
| 3 |
(1) Construction of RCC Road & 1 nos Cross Drain from Wazed Sarok to Wapda Road via Ward divider road (ch.00 to 170.00m) at Ward#02, 03 under Galachipa Pourashava. |
" |
35800 |
180 Days |
| 4 |
(1) Construction of RCC drain from Godawn Road west side to Pourashava RCC drain and drain from Samsul Haque house to cannal at Ward#01,02 under Galachipa Pourashava. |
" |
34000 |
180 Days |
| 5 |
(1) Construction / extention of Varandha of Al-Aksa Jame Mosjid at Ward#02 under Galachipa Pourashava, (2) Improvement / Repairing of Jainpuri Khankay at Ward No.-02 under Galachipa Pourashava. |
" |
20800 |
150 Days |
| 6 |
Constraction of RCC ghatla near Santi Paul Mill Road at ward no 06 under Galachipa pourashava |
" |
22000 |
180 Days |
| 7 |
(1) Construction of RCC road from Sarshina Khankay More to Samsul Haque Mollah bari Jame Mosjid at Ward#03 under Galachipa Pourashava. |
" |
17300 |
180 Days |
| 8 |
(1) Improvement of Road side shoulder by earth filling and protection work at ward no.-01, 03, 09 under Galachipa Pourashava. |
" |
28800 |
180 Days |
| 9 |
(1) Construction of (A) overlay CC road with shallow drain from Girls School Road to Manosha Mandir and Construction of Manosha Mandir (B) CC road of WAPDA Calony road, (C) CC Road WAPDA road Jabed Mia house at Ward#04 under Galachipa Pourashava. |
" |
21700 |
180 Days |
| 10 |
(1) Road side extention with Repair of CC road with guidewall Eusuf Sir lane at ward no.-04 under Galachipa Pourashava. |
" |
2900 |
90 Days |
| 11 |
(1) Improvement of earthen road from Food Godawn road to poura berybundh and Food Godawn road to Abdul Gani Mia School at Ward# 01,02 under Galachipa Pourashava. |
" |
9800 |
120 Days |
| 12 |
Construction of CC road from High School road to Ex. Upazila Chairman Md. Manik Mia House at ward no.-05 under Galachipa Pourashava. Ch.00-67.5m, |
" |
24300 |
180 Days |
| 13 |
(1) Construction of Graveyeard Boundary Wall of Hazi Bari, Dafader bari, Mallick bari at ward no.-06 under Galachipa Pourashava. |
" |
8100 |
120 Days |
| 14 |
(1) Construction of CC road from T&T road to House of Mr.Abu Taleb Mia house at ward no -06 Under Galachipa Pourashava. |
" |
12300 |
90 Days |
| 15 |
(1) Constraction of RCC ghatla of Fatik Bari pond at ward no 06 under Galachipa pourashava, (2) Repair of CC Road with protection wall T&T lane at ward no -06 under Galachipa Pourashava. |
" |
9900 |
90 Days |
| 16 |
(1) Construction of RCC Drain of Anondopara Kiro Road & Jahor Babu house drain at Ward#07 under Galachipa Pourashava. |
" |
50200 |
180 Days |
| 17 |
(1) Construction of (A) BFS road from Mannan Mia house to Nazrul Mia house(Near Makbul Sir house) & CC Road Mojibor Master House, (B) CC road from Arifur Rahman Sarok to Asraf Mia house & Amir Mia house at Ward#07 under Galachipa Pourashava. |
" |
23800 |
150 Days |
| 18 |
(1) Construction of RCC drain (A) Near Nasir Maji house lane, (B) Beside Dr. Khalek house to Palloby road, (C) Anondopara connecting drain near Anower driver house at Ward#07 under Galachipa Pourashava. |
" |
38400 |
150 Days |
| 19 |
(1) Construction of Girls School road widening adjacent Kalibari Mondir at Ward#04 under Galachipa Pourashava, (2) Construction of road from backside of Jasim Mia house to Chunnu Mokter house via Salim house |
" |
25000 |
150 Days |
| 20 |
(1) Construction of BFS & CC road From Main Road to Different house at ward no.-09 under Galachipa Pourashava. |
" |
63600 |
180 Days |